Shovel & Loader Productivity

Bank tonnes per hour and cost per tonne. Pick the material you are digging and density, swell, bucket fill and digging class fill themselves from published tables. Every number shows its working and its source.

A hydraulic mining shovel loading a haul truck at a blasted rock face

Step 1: What are you digging?

This one choice sets four values below. Override any of them if you have site data.

Step 2: The machine and the bench

Defaults are a mid-size shovel on a well-set-up bench.

bank tonnes / hour
cycle time, seconds
cost / bank tonne
StepValueWhere it comes from

Swing angle

What the hour actually buys

Material reference table: bank density, swell, fill factor and digging class
MaterialBank density (t/m³)lb/yd³ SwellFill factorDigging class

Atkinson 1992, via the SME Mining Engineering Handbook, Table 10.4-1 (p. 933). All 37 materials from the printed table are listed here: verified against the page. If your material is not in the list, pick the closest match by hardness and density, or enter your own values; each field can be overridden.

One limit worth knowing. The cycle-time table covers buckets from 3 to 35 m³ (4 to 45 yd³). Inside that range the calculator interpolates between published sizes. Outside it, the answer is extrapolated beyond what the source measured. It will still give you a number, but treat it as an indication rather than an estimate.